Paving in our Township

Updated: 18 hours ago

West Pikeland Township contractors will begin paving the following roads starting August 1:


PLEASE NOTE: The Township contractor is running ahead of schedule and dates may change


August 2 - 3 - Milling

Meredith Lane, Tullamore Circle, Oakhill Road


August 4 - 5 - Milling

Horseshoe Trail Rd., Eagle Farms Rd


August 4 - Milling

Hark-a-Way Rd, Tally Ho Lane, Chase Lane


August 8 - Milling

Evergreen Lane, Fieldstone Drive


August 10 - Base Repair

Oakhill Road, Horseshoe Trail Rd


August 9 - Paving

Meredith Lane, Tullamore Circle, Oakhill Road


August 10 and August 11 - Paving

Horseshoe Trail Rd., Eagle Farms Rd


August 12 - Paving

Hark-a-Way Rd, Tally Ho Lane, Chase Lane


August 15 - Paving

Evergreen Lane, Fieldstone Drive


August 15 to 16 - Joint Sealing

Meredith Lane, Tullamore Circle, Oakhill Road, Horseshoe Trail Rd., Eagle Farms Rd., Hark-a-Way Rd, Tally Ho Lane, Chase Lane, Evergreen Lane, Fieldstone Drive


This project consists of milling and paving of the existing roads.


During the course of the work, there will be times when the roadway has limited or no availability. The contractor plans to make the disruptions as minimal and as quick as possible. The contractor will perform work from Mondays-Fridays 7:00 AM to 5:00 PM.

We would like to thank you in advance for your patience and understanding during this construction project. If you should have any questions or concerns regarding this project, please feel free to contact the Township Engineer at 610-833-1784