West Pikeland Township contractors will begin paving the following roads starting August 1:
PLEASE NOTE: The Township contractor is running ahead of schedule and dates may change
August 2 - 3 - Milling
Meredith Lane, Tullamore Circle, Oakhill Road
August 4 - 5 - Milling
Horseshoe Trail Rd., Eagle Farms Rd
August 4 - Milling
Hark-a-Way Rd, Tally Ho Lane, Chase Lane
August 8 - Milling
Evergreen Lane, Fieldstone Drive
August 10 - Base Repair
Oakhill Road, Horseshoe Trail Rd
August 9 - Paving
Meredith Lane, Tullamore Circle, Oakhill Road
August 10 and August 11 - Paving
Horseshoe Trail Rd., Eagle Farms Rd
August 12 - Paving
Hark-a-Way Rd, Tally Ho Lane, Chase Lane
August 15 - Paving
Evergreen Lane, Fieldstone Drive
August 15 to 16 - Joint Sealing
Meredith Lane, Tullamore Circle, Oakhill Road, Horseshoe Trail Rd., Eagle Farms Rd., Hark-a-Way Rd, Tally Ho Lane, Chase Lane, Evergreen Lane, Fieldstone Drive
This project consists of milling and paving of the existing roads.
During the course of the work, there will be times when the roadway has limited or no availability. The contractor plans to make the disruptions as minimal and as quick as possible. The contractor will perform work from Mondays-Fridays 7:00 AM to 5:00 PM.
We would like to thank you in advance for your patience and understanding during this construction project. If you should have any questions or concerns regarding this project, please feel free to contact the Township Engineer at 610-833-1784